Citizens' Oversight Committee » Project Updates

Project Updates

Overview of Measure 'V' projects and construction updates

2017-19 Projects By Construction Type

DIGITAL MARQUEES

Installation of electronic marquees began in November 2017. Withrow Elementary School was the first to be installed. Seven school marquees will be completed by the end of November, and ready to be powered up, programed, and released for site use. Training on the use of the new marquee systems is in progress.

 
Installations since November 2017:
  • Cottonwood Canyon ES
  • Donald Graham ES
  • Railroad Canyon ES
  • ESWithrow ES
  • David A Brown Middle School
  • Elsinore Middle School

SAFETY IMPROVEMENTS

Measure V security vestibule construction at Terra Cotta Middle School

VIDEO UPDATES

 
 